Q106. - (Topic 2) 

Your team uses Microsoft Test Manager (MTM) to manage test cases. Your team organizes test cases so that the same test case can be associated with multiple test suites. 

You plan to create a test case and associate it to two different static test suites named Test Suite 1 and Test Suite 2. 

You need to ensure that the test suites reference the same version of the new test case. 

Which two actions should you perform? Each correct answer presents part of the solution. 

A. Drag the test case from Test Suite 1 into Test Suite 2. 

B. Create the test case inside Test Suite 1. 

C. Copy the test case from Test Suite 1, and paste it onto Test Suite 2. 

D. Right-click on the test case, and select Create a copy and add to test suite. 

Answer: B,C 

Explanation: http://msdn.microsoft.com/en-us/library/dd286659.aspx 


Q107. DRAG DROP - (Topic 1) 

Your company has a Microsoft Visual Studio Team Foundation Server (TFS) 2013. The company uses a Microsoft SharePoint instance as part of the physical TFS setup. 

The IT department is configuring scheduled backups. 

You need to grant the system administrators the appropriate permissions to configure the scheduled backups. 

Which permissions or roles should you assign to the system administrators? To answer, drag the appropriate permissions to the correct system. Each permissions may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content. 

Answer: 

Topic 2, Volume B 


Q108. - (Topic 3) 

Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage the software development process. You use the Microsoft Visual Studio Scrum 2013 process template on your TFS Team Project. 

You work with the product owner to define and prioritize the Product Backlog. 

Due to new business regulations, a group of product backlog items need to be implemented sooner than initially planned. 

You need to raise the business value of the affected product backlog items. 

Which two actions should you perform? Each correct answer presents a complete solution. 

A. Edit the Product Backlog Item work item by changing the resolution to a higher value. 

B. Select the Product Backlog Item, and drag it towards the top of the backlog. 

C. Adjust the business value on the Product Backlog Item. 

D. Edit the Product Backlog Item work item by changing the priority to a higher value. 

E. Select the Product Backlog Item, and drag it towards the bottom of the backlog. 

Answer: A,C 


Q109. - (Topic 2) 

You plan to roll out Microsoft Test Manager (MTM). Phase 1 testing will include manual testing only. In Phase 2, you will introduce automated test suites to complement manual testing. 

You plan to use diagnostic data adapters for each phase. 

You need to provide the correct diagnostic data adapters. 

Which data diagnostic adapter is only applicable to manual testing and would accomplish this goal? 

A. Code coverage 

B. Actions 

C. Video Recording 

D. Event Log 

E. Test impact 

Answer:


Q110. DRAG DROP - (Topic 1) 

Several of your company programmers are at a remote location. They are sharing files with the main office. 

You need to set up a Team Foundation Server Proxy at the remote location to reduce bandwidth usage. 

Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order. 

Answer: 


Q111. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS) 2012 server. Your development team has a Visual Studio solution file that is used to build a software product. 

A developer reports that when he retrieves the latest source file to his computer from TFS and performs a build, the build frequently breaks. 

You need to provide a solution that prevents check-ins to TFS that will break developers’ builds. 

What should you do? 

A. Configure a Team Build for the project and set the build trigger to Continuous Integration. Then modify the build template to automatically roll back check-ins from failed builds. 

B. Configure a Team Build for the solution and set the trigger to Gated Check-in. 

C. Configure a Team Build for the solution and set the trigger to Schedule. Then modify the build template to automatically roll back check-ins from failed builds. 

D. Configure a Team Build for the project and set the build trigger to Continuous Integration. 

Answer:


Q112. - (Topic 2) 

You are using Microsoft Test Manager (MTM) to create a test plan for testing an ASP.NET website. 

Your test plan needs to validate a set of critical business functionalities for the current sprint. All business functionalities are documented in the requirements document published to the project portal. 

You need to associate your test plan with the requirements document. 

What should you do? 

A. Add a link to the requirements document in the Links section of the Properties view of the test plan. 

B. Click Copy Link in the Properties view of the test plan to link the requirements document on the project portal to the test plan. 

C. In the Area path drop-down list in the Properties view of the test plan, right-click the test plan area path node relevant to the requirements being tested. Select Add link to associate the requirements document link on the project portal with the area path node. 

D. Click Link next to the Description box in the Properties view of the test plan to link the requirements document on the project portal to the test plan. 

E. Click Link next to the Name box in the Properties view of the test plan to link the 

requirements document on the project portal to the test plan. 

Answer:

Topic 3, Volume C 


Q113. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server that uses default ports for communication. Visual Studio 2012 has been installed on your computer recently. 

You need to connect to the TFS server. 

What are two possible options for entering Name or URL in the Connect to TFS dialog box? (Each correct answer presents a complete solution. Choose two.) 

A. Tfs1 

B. http: //tfs1: 8080/tfs 

C. http: //tfs1: 8080 

D. http: //tfs1 

Answer: A,B 


Q114. - (Topic 2) 

You are using Microsoft Test Manager (MTM). 

You need to develop test cases that trace to a set of requirements. 

What should you do? 

A. Add the requirements as test step attachments. 

B. Add links from the test cases to the requirements. 

C. Add links from the test suite to the requirements. 

D. Add the requirements as test case attachments. 

Answer:


Q115. - (Topic 1) 

Your company has a deployment of Microsoft Visual Studio Team Foundation Server (TFS), as well as a proxy server at a development site in a different country. 

You need to ensure that the proxy server can communicate with the TFS at headquarters via your company WAN. 

Which network port should you use? 

A. 80 

B. 443 

C. 8080 

D. 8081 

Answer:

Explanation: http://msdn.microsoft.com/en-us/library/ms181475.aspx 


Q116. - (Topic 1) 

Your network environment includes a Microsoft Visual Studio Team Foundation Server 2012 (TFS) server. 

Version control is configured with one project collection and two team projects. Some users use 2010 and 2012 clients, such as Visual Studio and Team Explorer Everywhere. 

You need to ensure that users will be prompted by, and can satisfy, the comments check-in policy when using both 2010 and 2012 clients. 

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.) 

A. Add the Changeset Comments policy in the team project collection’s source control settings. 

B. Add the Changeset Comments policy in the source control settings for each team project. 

C. Install the TFS 2010 Power Tools on all clients. 

D. Install the TFS 2012 Power Tools on all clients and configure the policy by using Team Explorer. 

E. Install the TFS 2010 and 2012 Power Tools on the TFS application tier and configure the policy by using Team Foundation Administrator. 

Answer: B,C 


Q117. - (Topic 2) 

You are using Microsoft Test Manager (MTM). 

You have a large list of existing test plans that are obsolete. These test plans should be kept for historical purposes. When testers click oi the Home button to select a test plan, the list is too long to easily navigate. 

You need to show only the test plans that are currently being used. 

What should you do? 

A. In the Test Plan Manager view, right-click each obsolete test plan and select Hide. 

B. In the Test Plan Manager view, for each obsolete test plan select Delete test plan. 

C. In the test plan Properties, change the State to Inactive for each obsolete test plan. 

D. In the Test Plan Manager view, right-click each obsolete test plan and select Close. 

E. In the test plan Properties, change the State to Closed for each obsolete test plan. 

Answer:


Q118. - (Topic 3) 

You are part of a scrum team that needs to identify user stories to complete in the next sprint. 

What should the scrum master do? 

A. Have the product owner decide which user stories to complete within the sprint. 

B. Order the user stories by their story points. Select the top stories based on the team's velocity. 

C. Have the team decide which user stories to complete within the sprint. 

D. The scrum master should decide which user stories to complete within the sprint. 

Answer:


Q119. - (Topic 1) 

You have upgraded an installation of Microsoft Visual Studio Team Foundation Server (TFS) 2013. 

You need to modify an existing project on which you want to enable portfolio management. 

What should you do? 

A. Update the application tier. 

B. Move team projects to a project collection. 

C. Update team projects with Team Explorer. 

D. Run the Configure Features wizard. 

Answer:

Explanation: http://msdn.microsoft.com/en-us/library/ff432837.aspx 


Q120. - (Topic 1) 

Your network environment includes a multi-tier Microsoft Visual Studio Team Foundation Server (TFS) 2012 server implementation. 

A member of the networking team changes the name of a user’s computer. 

From the user’s computer, you need to modify the existing workspace to reflect the new computer name. 

What should you do? 

A. Execute the following workspaces command to update the machine name: tf workspaces/updateCornputerName: <oldcomputername> /collection: http: //tea mserver: 8080/tfs/ DefaultCollection. 

B. Create a new workspace. Replace the existing workspace with the new one by using the Manage Workspaces window in Source Control Explorer. 

C. Execute the following workspace command to update the machine name: tf workspace /computer: <oldcomputername> / collection: http: //teamserver: 8080/tfs/ DefaultCollection. 

D. Open the existing workspace by using the Manage Workspaces window in Source Control Explorer. In the Computer field, enter the new machine name. 

Answer: